Closing Out a Job: Punch Lists, Affidavits, and Final Releases

A job can be finished in the field and still be wide open on paper. The crew has demobilized, the customer is using the space, and everyone involved considers it done — but the final payment has not moved, the release forms are not signed, and the job is still collecting costs in the accounting file.

Closing a job is a separate task from finishing one. In Florida it runs on statutory deadlines that do not wait for the paperwork to catch up.

Finishing the Work Is Not Closing the Job

Most jobs stall at the same point. The work is substantially complete, a short punch list remains, and the file sits in a state nobody owns: too finished for the field to chase, not finished enough for the office to bill out and close.

That gap is where final payment and retainage sit. It is also where lien rights quietly expire.

The Lien Clock Runs From Final Furnishing, Not From the Punch List

This is the part most often misread. Under Fla. Stat. §713.08(5), a claim of lien must be recorded no later than 90 days after final furnishing of labor, services, or materials.

"Final furnishing" is defined in Fla. Stat. §713.01(12) as the last date the lienor furnishes labor, services, or materials — and the statute is explicit about what does not count. That date "may not be measured by other standards, such as the issuance of a certificate of occupancy or the issuance of a certificate of final completion, and does not include the correction of deficiencies in the lienor's previously performed work or materials supplied."

Read that against how a punch list actually gets worked. Returning in November to fix something you already installed is correction of deficiencies. It does not restart the 90 days. Neither does the certificate of occupancy, and neither does the owner finally signing off on completion.

So the practical risk is the opposite of how it feels. A job that drags through a long, informal punch-list phase feels more open, and the lien deadline is running the entire time — measured from work you finished months earlier.

These are legal deadlines, not bookkeeping preferences. What we can do is make sure the dates are visible in the file; when a deadline is close or a payment is genuinely in dispute, that is a conversation for construction counsel, not a ledger entry.

The Final Payment Affidavit Comes Before Final Payment

On a direct contract with the owner, the contractor's final payment affidavit under Fla. Stat. §713.06(3)(d) is not a formality to be produced later. Two things in that subsection set the sequence.

First, the owner is required to hold the money: the statute says the owner "shall retain the final payment due under the direct contract that shall not be disbursed until the contractor's affidavit ... has been furnished to the owner." If the affidavit is not in, the final payment is not supposed to move. Chasing the check before the affidavit is out is chasing a payment the owner is directed to withhold.

Second, the affidavit is a prerequisite to enforcement. It must be furnished at least 5 days before instituting an action to enforce the lien, and while a contractor is in default for not giving it, the statute provides that the contractor "shall have no lien or right of action against the owner for labor, services, or materials furnished under the direct contract."

The affidavit states whether all lienors under the direct contract who timely served a notice to owner have been paid in full, and if not, names each one and the amount due. That is a statement about your payables — which means it can only be signed truthfully if the subcontractor and supplier records for that job are actually current.

The Final Release Has a Statutory Form

Florida prescribes the release forms. Fla. Stat. §713.20 sets out "WAIVER AND RELEASE OF LIEN UPON PROGRESS PAYMENT" in subsection (4) and "WAIVER AND RELEASE OF LIEN UPON FINAL PAYMENT" in subsection (5).

Two provisions matter at closeout:

The distinction between the progress form and the final form is the one that gets missed in a hurry. Signing the final release to unlock a payment that is not actually final gives away the balance.

Releases From Everyone Below You

The affidavit you sign describes whether the people under you have been paid. So closeout runs downward before it runs upward: final releases from subcontractors and suppliers, matched against the job's payables, before the final release goes up to the owner.

If a sub is slow to return a release, Fla. Stat. §713.346 is the relevant pressure. It requires payment of undisputed obligations in accordance with the contract, and subsection (2) sets a 30-day period — running from when the labor or materials were furnished and payment became due, or from when payment was received, whichever occurs last — after which the statute's dispute procedures and remedies become available.

One caution, because it circulates widely: Florida does not impose a blanket 14-day deadline for releasing retainage on private jobs. Retainage release on private work is governed by the contract. Public work is different, and Fla. Stat. §255.078 governs there; retainage and progress payments covers that split. Check the contract before quoting a deadline at anyone.

Closing the Job in the Books

The statutory chain above is what ends the job legally. Something else has to end it in the accounting file, or the job keeps moving after you have stopped watching it.

A Job Closeout Sequence

  1. Fix the final furnishing date for the job and write it down. Count 90 days from it.
  2. Finish and document the punch list — knowing that correction work does not extend the date in step 1.
  3. Collect final releases from subcontractors and suppliers on the §713.20(5) form.
  4. Reconcile job payables against those releases.
  5. Furnish the final payment affidavit to the owner under §713.06(3)(d).
  6. Bill everything remaining, including approved change orders.
  7. Request retainage on the terms the contract actually states.
  8. Sign the final release only when the payment is genuinely final.
  9. Close the job in the books, accrue known late costs, and file the final job cost report.

How KDM Accounting Services Can Help

At KDM Accounting Services, we work the office half of closeout for Florida contractors. We can:

We do not practice law and we do not run your site. Lien deadlines and release language are questions for construction counsel. What we keep straight is the record those documents have to describe.

Close the Job, Not Just the Site

A job that is finished in the field and open on paper is still consuming attention, still holding cash, and — where lien rights are concerned — still running out a clock measured from work that ended months ago.

The closeout sequence is short and it is the same every time. Running it deliberately turns a finished job into a collected one.

If you want help getting the job file closed, contact KDM Accounting Services. We'll help you get the record straight before the paperwork is the only thing left holding the money.

Frequently Asked Questions

Does finishing punch list work extend my Florida lien deadline?

No. Fla. Stat. §713.01(12) defines final furnishing as the last date you furnished labor, services, or materials, and expressly excludes the correction of deficiencies in your own previously performed work. The 90-day recording deadline in §713.08(5) runs from that date, so returning to fix earlier work does not restart it.

Can the owner pay me before I hand over the final payment affidavit?

Fla. Stat. §713.06(3)(d) directs the owner to retain the final payment under the direct contract until the contractor's affidavit has been furnished. It is also a prerequisite to enforcing a lien, and must be furnished at least 5 days before instituting an action.

Do I have to sign a custom lien release a general contractor sends me?

Fla. Stat. §713.20(6) provides that a person may not require a lienor to furnish a release different from the statutory forms in §713.20(4) and (5). Be aware that §713.20(8) makes a non-conforming release enforceable on its own terms if you sign it anyway.

LET’S START WITH YOU

Free consultation

A few details to help us understand your needs.

Add business details Optional

Required fields marked *
Please don’t include tax IDs or financial documents.

Call KDM (561) 334-4066